HomeMy WebLinkAbout10.01.26 Board Correspondence - FW_ Request for Delay of Action_Extension of Time submitted in FERC P-803-000 by Pacific Gas and Electric CompanyFrom:Clerk of the Board
To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Dubose, Teri; Durfee, Peter; Jessee, Meegan;
Kimmelshue, Tod; Kitts, Melissa; Krater, Sharleen; Lee, Lewis; Ritter, Tami; Simmons, Katie; Stephens, Brad J.;
Sweeney, Kathleen; Teeter, Doug; Zepeda, Elizabeth
Cc:Cannon, Jamie; Loeser, Kamie
Subject:Board Correspondence - FW: Request for Delay of Action/Extension of Time submitted in FERC P-803-000 by
Pacific Gas and Electric Company
Date:Thursday, October 1, 2026 3:37:20 PM
Please see Board Correspondence -
Lewis Lee
Administrative Technician - Confidential
Butte County Administration
25 County Center Drive, Suite 200 • Oroville, CA 95965
T: 530.552.3326
www.buttecounty.ca.gov | lelee@buttecounty.ca.gov
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Thursday, October 1, 2026 12:06 PM
Subject: Request for Delay of Action/Extension of Time submitted in FERC P-803-000 by Pacific Gas and Electric
Company
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening
attachments, clicking on links, or replying..
On 10/1/2026, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC),
Washington D.C.:
Filer: Pacific Gas and Electric Company
Docket(s): P-803-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Request for Delay of Action/Extension of Time
Description: Pacific Gas and Electric Company submits request for an extension of time until 06/15/2027 to
address FERC's Comment 2 re an updated Probable Maximum Flood Study et al. re the Round Valley Dam of the
DeSabla-Centerville Hydroelectric Project under P-803.
To view the document for this Filing, click here
https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20261001-
5259__;!!KNMwiTCp4spf!BprAw-95KqlhlJ-wFg1-wMs8PqZzurtN-98pIj3rbLROHRy-
R9K8n1rdhlgRgyZYdNb8rJ77cfThHeHSwtRbBmqWyDL6tHsqQ35h$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!BprAw-95KqlhlJ-
wFg1-wMs8PqZzurtN-98pIj3rbLROHRy-R9K8n1rdhlgRgyZYdNb8rJ77cfThHeHSwtRbBmqWyDL6tG3GSu_c$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!BprAw-95KqlhlJ-wFg1-
wMs8PqZzurtN-98pIj3rbLROHRy-R9K8n1rdhlgRgyZYdNb8rJ77cfThHeHSwtRbBmqWyDL6tMS1BLcB$
or for phone support, call 866-208-3676.
Power Generation 300 Lakeside Drive
Oakland, CA 94612
Mailing Address:
P.O. Box 28209
Oakland, CA 94604
October 1, 2026
Via Electronic Submittal (E-File)
Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: DeSabla-Centerville Hydroelectric Project, FERC No. 803-CA
Round Valley Dam, NATDAM No. CA00346
Updated Probable Maximum Flood Study – FERC Comment 2
Second Part 12D Inspection – Recommendations 14 and 15
Extension of Time Request
ENCLOSURE CONTAINS CUI//CEII – DO NOT RELEASE
Dear Frank L. Blackett:
This letter presents Pacific Gas and Electric Company’s (PG&E) request for an extension of time to
address the Federal Energy Regulatory Commission’s (FERC) Comment 2 (C-2) from a letter
dated August 10, 2021, and Recommendations 14 and 15 (R-14 and R-15) from the second Part
12D safety inspection report (dated November 2, 2020) for Round Valley Dam, which is part of
PG&E’s DeSabla-Centerville Hydroelectric Project, FERC No. 803. In accordance with Title 18 of
the Code of Federal Regulations, Section 12.40(d), PG&E has included a reasoned basis for this
extension of time request. PG&E submitted its initial plan and schedule to address C-2 in a letter
dated August 31, 2021; PG&E submitted its initial plan and schedule for addressing R-14 and R-15
in a letter dated December 31, 2020. PG&E’s most recent transmittal, dated March 27, 2024,
included extension of time requests for C-2, R-14, and R-15.
The extension of time requests for C-2, R-14, and R-15 and reason for the request are enclosed
with this letter (Enclosure 1). Should you have technical questions concerning this matter, please
contact Isabelle Rawlings, senior dam safety engineer for PG&E, at (925) 359-5420. For general
questions, please contact Andrew Garcia, license coordinator for PG&E, at (530) 228-8990.
Sincerely,
Robert O. Ellis, P.E., G.E.
Deputy Chief Dam Safety Engineer
Enclosure: CUI//CEII – DO NOT RELEASE
1. Extension of Time Request